CAPITAL INVESTMENTS | WATER
Recycled Water Treatment Plant Chlorination Improvements
DESCRIPTION
| PROJECT ID: | S 25.0 |
| ESTIMATED COST: | $1,200,000 |
| ACTUAL COST: | TBD |
- Replaces existing gas chlorine treatment equipment at the Recycled Water Treatment Plant.
WHY IT’S NEEDED
The city’s draft National Pollutant Discharge Elimination System Permit renewal document sets new limits on discharging chlorine byproducts on the treatment plant effluent, which are not achievable when gas chlorination methods are continued to be used.
PROJECT STATUS:
In Progress
PROJECT MILESTONES
March 2026
City Council awards construction contract to Glasco UV Ultraviolet Light Technologies.
Spring 2026
Project advertised.
Summer 2025
Design begins.
LAST UPDATED: 06/29/26